[ecis2016.org] Assuring that the Hyderabad Metro Rail project is on schedule, its managing director has revealed that the safety trials for the second stage from Miyapur to SR Nagar, will begin soon
The safety certification trials of the 12-km Miyapur-SR Nagar stretch of Hyderabad Metro Rail (HMR) project will be conducted soon, a top official said.
You are reading: Hyderabad Metro: Safety trials on Miyapur-SR Nagar stretch soon
Read also : Property rates & trends in Thiruvanmiyur, Chennai
“We have completed 58 kms of the metro’s foundations, 56 kms of pillars and 46 kms of viaduct, and work on both the depots have been completed. For the Nagole-Mettuguda 8-km stretch, the Commissioner of Metro Rail Safety (CMRS) has already given the safety certification. The second stage of Miyapur-SR Nagar (12 km) stretch, will go for safety certification trials very soon,” HMR managing director, NVS Reddy said.
“The project is on schedule and going on well. There are still some hurdles and we will overcome them,” Reddy said.
[ecis2016.org] Hyderabad ORR between Shamirpet and Ghatkesar inaugurated
Read also : Two non-bank lenders take Rashmi Housing to NCLT, for default on Rs 26-crore payment
L&T Metro Rail Hyderabad (L&TMRH), is developing the 72-km elevated Hyderabad Metro Rail project, which will have three corridors and 66 stations. The HRM Project is the world’s largest public-private partnership project (PPP) in the sector. The metro network will cover a total distance of around 72 kms, across three corridors.
The project was initially scheduled to be completed by July 2017, but delays like changes in alignment, land acquisition and other issues, have resulted in the project overshooting the deadline. All three metro rail corridors, including the one passing through the Old City, are expected to be completed by December 2018, authorities earlier said.