[ecis2016.org] The Kolkata Metro has passed a significant milestone on the East-West corridor, by completing the tunneling work under a busy part of the city that houses heritage buildings

A critical phase of tunneling under the busiest part of the city, which houses a number of heritage buildings, was completed by the Kolkata Metro Rail Corporation, on March 22, 2018, a Metro official said. Starting from Howrah Maidan on the other side of the Hooghly, the west-bound line tunnel boring machine ‘Prerna’ reached Esplanade metro station, covering a distance of 3.8 kms, after passing under the river, the official said.

You are reading: Kolkata Metro completes tunneling under heritage buildings

Read also : Green panel approves Rs 2,600-crore Hyderabad airport expansion plan

The tunneling had begun at Howrah Maidan on April 21, 2016 and took 23 months to pass under the Hooghly river, the Burrabazar wholesale business hub and several heritage buildings in Benoy Badal Dinesh Bagh, also called the Dalhousie area, to reach Esplanade in the heart of the city. “Engineers and technicians from different countries joined hands with Indian experts, to complete this task meticulously,” the official said.

The tunnel, crossing below the Hooghly, is the first transportation tunnel in the country under any river, he said. Beth El and Magen David synagogues, St Andrews church, Writers Buildings (the secretariat), Old Telegraph office and Raj Bhawan and Esplanade Mansion, are some of the important buildings under which tunneling was done.

[ecis2016.org] Allot more funds for Kolkata Metro: Parliamentary panel

Read also : Everything about GVMC water tax

“Necessary protective measures and continuous monitoring was adopted, to avoid any impact on those structures,” the official said.

The tunnel also passed under several dilapidated buildings in the Burrabazar area and measures like translocation of inhabitants were taken, to ensure safety during the tunneling. The 16.6-km-long East-West Metro is scheduled to be completed by June 2021. It will have an underground corridor of 10.8 kms and the elevated section will be of 5.8 kms, the official added.

Source: https://ecis2016.org/.
Copyright belongs to: ecis2016.org

Source: https://ecis2016.org
Category: Lifestyle

Debora Berti

Università degli Studi di Firenze, IT

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button