Bullet train land measuring process suspended, due to MNS’ protest

[ecis2016.org] Maharashtra Navnirman Sena workers have forced the suspension of the work of measuring land that needs to be acquired for the Mumbai-Ahmedabad high speed rail corridor, popularly called the bullet train project

Officials have said that the process of measuring the land that needs to be acquired for the Mumbai-Ahmedabad high speed rail corridor, was suspended on May 7, 2018, after workers of the Maharashtra Navnirman Sena (MNS) disrupted the process several times. The wok was suspended in the afternoon, despite the presence of a posse of police, after the mob opposing it grew in numbers considerably. The land measurement process was being undertaken in the Shilphata area of Shil village in neighbouring Thane district, by the state’s Public Works Department.

You are reading: Bullet train land measuring process suspended, due to MNS’ protest

Read also : PropTiger launches experiential platform ‘PropTiger Direct’ for virtually immersive property hunting

[ecis2016.org] Bullet train land row: Railways to offer higher compensation to farmers

“We will continue to oppose this measurement drive, as we want jobs and not a bullet train. There will be flash protests as well, to force the authorities to suspend the work,” said Avinash Jadhav, MNS’ Thane district chief. The party, tweeting from its official Twitter handle @mnsadhikrut, alleged that the bullet train project was a ploy to separate Mumbai from Maharashtra. “It is clear that the bullet train project is an attempt to separate Mumbai from Maharashtra. Raj Thackeray had already announced of not allowing erection of a single brick of the train project. The government should not thrust the project upon us,” the MNS’ tweet read.

Read also : Cities should raise funds from local markets: Venkaiah Naidu

The MNS further said on the micro-blogging site that in case the land measurement process for the rail corridor continued, the party would escalate opposition to it, in its ‘own style’. MNS chief Raj Thackeray has been a vocal opponent of the multi-billion dollar project and has, during his public rallies, appealed to farmers along the route of the high speed corridor, to not allow the Railways to acquire their lands.

The 508-kilometre Mumbai-Ahmedabad bullet train project, estimated to cost Rs 1,08,000 crores, is being built with the Japanese government providing a loan to cover 81 per cent of the cost. The project, being constructed by a special purpose vehicle called the National High Speed Rail Corporation (NHSRC), is targeted for commissioning by 2022-23.

Source: https://ecis2016.org/.
Copyright belongs to: ecis2016.org

Source: https://ecis2016.org
Category: Lifestyle

Debora Berti

Università degli Studi di Firenze, IT

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button